DIGITAL ENERGY CAPACITY

How much flexible load can the grid serve?

The capacity available for new demand at a grid connection can rise and fall throughout the day. Digital Energy Capacity measures how much of that headroom a specific workload could use, where, and for how long.

ONE CONNECTION POINTILLUSTRATIVE DAY
420 00:0006:00 12:0018:0024:00
Local headroom (MW). More capacity is available overnight and less during the afternoon. A continuous load has to fit even in the most constrained hours.

THE MEASURE

Capacity depends on what you need to run.

Developed within Ex³ Energy’s Computational Energy Framework, DEC estimates how much additional load a grid can accommodate at a given location and over a defined period, subject to grid limits and the workload’s operating requirements.

Where is there headroom?

Start at the point of connection. Lower regional demand can point to promising hours; local equipment and network limits determine what can fit there.

What can actually move?

Separate protected load from work you can schedule. Account for deadlines, interruptions and any rebound demand when that work resumes.

What can the project plan around?

Compare an earlier flexible phase with waiting for firm service. Identify the required hours, limits and fallback, and verify them against utility service terms.

THE ENGAGEMENT

Phase 1 Power & Delivery Review

Our first application: Texas data center development.

A decision memo for your team

Compare firm, phased and flexible options. See which workloads a first phase could support and what to verify before committing IT capacity or a handover date.

An evidence table for the next milestone

See which power terms and tenant requirements support each option, who can close each open item, by when, and what to do if it slips.

A fixed scope and fee

We agree the fee up front. Delivery is five business days after we receive the complete, authorized inputs agreed in scope.

ILLUSTRATIVE EXAMPLE

Same energy. Two different outcomes.

At this connection point, available capacity is 4 MW overnight, 2 MW in the morning and evening, and 0.5 MW in the afternoon. Compare two ways of using 24 MWh in a day.

Hypothetical meter-level example. Both profiles assume all electrical loads are already included. A live review tests the limits, service terms and workload requirements for the actual site.

Choose a load profile

FITS THE ILLUSTRATIVE WINDOW

24 of 24 MWh

4 MW × 6 hours. All the work fits before 06:00, assuming it can run entirely in that window.

THE PRODUCT WE’RE DEVELOPING

A shared planning tool for grids and flexible loads.

We’re starting with project reviews in Texas. The longer-term goal is a DEC engine that system operators and large loads can use across markets to compare usable capacity windows under local constraints and rules.

Data centers

Evaluate whether schedulable computing can run in an earlier phase while protecting always-on workloads.

EV charging

Compare charging schedules that respect connection limits and still meet vehicle departure targets.

Automated factories

Test whether energy-intensive batches can move without missing production deadlines or interrupting continuous processes.

For grid operators and utilities: We’re interested in pilot partners to test how local grid limits, connection terms and real load profiles can be evaluated together. Discuss a pilot.

TALK WITH EX³ ENERGY

Could a flexible first phase work at your site?

Start with a 20-minute conversation. No documents are needed for the first call. If we go forward, we agree on a secure channel before you share sensitive material.

Santiago Parra

Founder, Ex³ Energy

Request a call by email santiago@ex3energy.com